Is anyone out there using MP75 consistently? On their video Knauf claims that a 2 and 1 gang can easily do 150m2 of plastering in a day. Is that right? I want to hear from someone who uses it all the time. And basically to give me an honest answer about what its like to use and the benefits and the disadvantages set against float and set with hardwall and finish.
stu
Fresh Boarder
Posts: 2
graphgraph
User Offline Click here to see the profile of this user
Please Register to submit a topic or to reply to this post.
 
#33
Re:MP75 Claims 1 Year, 1 Month ago Karma: 2
If YOU spay mp75 just do 50 meters a day per man if it is in big rooms it is lovely stuff to use, any thing blocks plaster board and just prime high suction backgrounds and spay it on. not like hard wall were you have to spay frist coat then clean the machine then get a drill out and mix up your setting coat and go over the same wall two times what a waste of time by the time you have done this with mp75 you have spayed it on finsh it and go home
patrick wait
make it pay spray
Fresh Boarder
Posts: 6
graphgraph
User Offline Click here to see the profile of this user
Gender: Male Location: eastbourne
Please Register to submit a topic or to reply to this post.
 
#71
Re:MP75 Claims 1 Year, 1 Month ago Karma: 0
its bloody hard work though if youre doing it properly
Ian Jones
Fresh Boarder
Posts: 12
graphgraph
User Offline Click here to see the profile of this user
Please Register to submit a topic or to reply to this post.
 
#94
Re:MP75 Claims 1 Year, 1 Month ago Karma: 0
I am working with mp75 every day,it is hard work if you dont now what you dooing.You cant do 50 meters in one set,you have to do two or three sets by 25 meters than you can get goot results
paulius
Fresh Boarder
Posts: 2
graphgraph
User Offline Click here to see the profile of this user
Please Register to submit a topic or to reply to this post.
 
#97
Re:MP75 Claims 1 Year, 1 Month ago Karma: 7
Hi,

How do you manage to do 3 sets in a day then? I think 2 sets makes for a long day, let alone three. I'd be interested to know how you do it.
Scott
Admin
Posts: 38
graph
User Offline Click here to see the profile of this user
Gender: Male Utiform Plastering Machines Location: All over the place!  But West Sussex mostly
Please Register to submit a topic or to reply to this post.
Keep machine plastering!

Scott
Utiform UK
 
#98
Re:MP75 Claims 1 Year, 1 Month ago Karma: 0
Hi,you can't do three sets and go home at 3 a clock you will finisf at 6 or 7 but if you dooing price work it's nise money.
paulius
Fresh Boarder
Posts: 2
graphgraph
User Offline Click here to see the profile of this user
Please Register to submit a topic or to reply to this post.
 
#99
Re:MP75 Claims 1 Year ago Karma: 0
fuck that
gary gibson
up the yids
Fresh Boarder
Posts: 3
graphgraph
User Offline Click here to see the profile of this user
Gender: Male Location: essex Birthdate: 1967-03-21
Please Register to submit a topic or to reply to this post.
 
#100
Re:MP75 Claims 1 Year ago Karma: 1
totally agree with grand ...... fuck that ....working til 6 or 7 then driving an hour home .........don't think so
ivor biggun
Fresh Boarder
Posts: 14
graphgraph
User Offline Click here to see the profile of this user
Please Register to submit a topic or to reply to this post.
 
Go to topPage: 1
get the latest posts directly to your desktop